This is the weekly update for the construction on Philhower Road between USH 51 and CTH G (Week of May 3rd, 2021).
- Current construction activities:
- PMI pulverized the existing roadway asphalt
- Rock Road finished installing all culverts
- Schultz placed curb & gutter at Bartells intersection with Philhower
- Rock Road began grading the roadway
- Upcoming construction activities:
- Rock Road will continue to grade the roadway and ditches (5/10 – 5/11)
- Highway Landscapers will restore ditches with seed, mulch and erosion mat (5/10 – 5/11)
- Rock Road will pave asphalt on Philhower Road and Bartells Drive (5/12 – 5/14)